Pavi Construction Update April 1-30

What a month! The pavi has been transformed from a partly finished shell to an almost summer-ready building…well, parts of it.

Progress could not be made without the help of so many volunteers! People have come from far (PA) and close (Lynds Hill Road) to help get the pavi ready for Summer 2015.

Progress also could not be made without the daily efforts of the Jenne Construction Crew. We’re thankful they braved the mud season & cold spring temps to keep moving the pavilion closer to finished!

Despite all the progress that’s been made during the month of April there remains quite a ways to go! Do you have anytime during the month of May to join us in getting the pavilion ready for summer? Email us or call the office to let us know when you can come. If you can’t come to help in May be sure to join us this summer! Bring a camper or come volunteer!

Read on for a recap of pavi work throughout the last month.  Click the link to see Pavilion Progress Pics and the people who have been doing the work.

Pavi Construction Update week of April 6
Another exciting week at BBC! A group of 13 are here from Salford Mennonite Church (Harleysville, PA). In one day (Tues) they’ve put decking on the porch roofs, started shingling, aided Harold Bergey with the electrical progress in the kitchen and continue to prepare the downstairs for insulation and sheet rock.  The crew of Jenne Construction continues to steadily move the pavilion towards completion. Pray for good roofing weather this week as many hands make the work light!

 

Pavi Construction Update: Week of April 13

There continues to be lots of action on the hill this week to move the pavilion towards a certificate of occupancy by June 1! Inside the building a team of electricians are finishing up the rough wiring and spending time on a lift to prepare the high pavi ceilings for lights. Many thanks to Harold Bergey who’s here for the third straight week and his posse of volunteers: Will Bergey, Marlin Bergey and Neil Bergey from Bergey’s Electric (Hatfield, PA). Andy Bird (Bridgewater, VT) has been volunteering his VT Masters license all week too! Roy Snell (Woodstock, VT) Ken Hershey and Larry Derstine (Bridgewater, VT) have spent 2 days shingling and siding. Nancy and Russell Pejouhy and Jeremy Ebersole (Tafstville, VT) have spent time staining interior boards. RFactor is here spraying insulation downstairs. On Tuesday Nevin and Job Mast (Oley, PA) spent the day installing piping for a central vac. Audie Bellimer (Bridgewater, VT) is making sure propane is ready to be used in the kitchen. Jon Blanch (Wallingford, VT) continues to spearhead the heating efforts. And the crew of Jenne Construction steadily contributes to pavi progress each day!

Pavi Construction Update – week of April 20:

Today marks 6 weeks exactly until we would like to gain conditional occupancy and start moving into the new pavilion.  In some ways, that seems like a long time. But it’s not!  There is much to be done before that point. If you’re able to give some time (or $$$) between now and June 1, please do!

This week a group of 10 guys from Blooming Glen Mennonite Church is volunteering.  R-Factor insulation experts are on site doing spray foam.  Jenne Construction is here, of course.  Local volunteers (Betsy Tonkin, Marcia Bender, Calef Hepler, Naomi Moyer, Joanne Hershey and others) are staining board after board.  Porches are being finished and then siding will continue with help from Ken Hershey, Roy Snell and Larry Derstine.  Roofing will continue as weather allows (it snowed some today, April 20).  Electrical rough in is nearly done and finishes are starting.  Pray with us for ongoing safety and good times.

Pavi Construction Update – Week of April 27: 

Harold Bergey is back to work with Andy Bird on underground electrical needs. Dale Snader of Dale’s homes donates time and machines to dig trenches. Ken Hershey and Larry Derstine contribute their carpentry expertise to every aspect of the building. John Blanch continues to move the heating work towards completion. Jenne Construction completes the shingling on the 2 story part while making headway on drywalling the kitchen. Tuna, Greg and Robert discuss phasing with the fire marshall in an effort to gain conditional occupancy by June 1.

Come join us and be part of the May Update!

Pic of Pavi on April 1, 2015
Pic of Pavi on April 1, 2015
Pic of Pavi taken May 1
Pic of Pavi taken May 1

 

See more pics here!

Search

Categories

Archives