Pavi Project Update: Kitchen completion continues

Since the last pavi update more progress has been made!  A faithful supporter gave $9,000 toward kitchen equipment so we bought the convection ovens and slicer. Huge upgrades!  You can see the updated pavilion project punch list below.

Here are the ovens being delivered:

And the ovens in place!

 

And the slicer:

 

And here is the punch list.  You can compare this to the one from a report this past December to see progress made.  Very exciting!

This is the list as of August 2017:

Onward!

Brandon “Tuna” Bergey